The Government’s unveiling of its road-building programme yesterday was ambitious and, many would say, long overdue.
But the question will be whether it is too ambitious, whether it is affordable, and, if not, what might be dropped.
The big ticket items will be the 17 so-called Roads of National Significance. (RoNS)
However, Transport Minister Simeon Brown’s plans for the next three years announced yesterday only include possible dates for projects in Northland, Auckland, Tauranga, Horowhenua, and Hawkes Bay.
The remainder are simply promises to build at some time in the future.
The 2024 – 27 Land Transport Work programme, which Brown launched yesterday, said the State Highway Investment Proposal 2024–34 (SHIP) proposed staging individual projects over three National Land Transport Programme (NLTP) periods.
“Planning is underway to set up a 10-year pipeline of work for all projects,” it said.
“This will give industry the confidence to plan long-term and make the necessary investments in equipment and staff to deliver at scale and pace.
“To inform the pipeline, we’ve grouped projects into three waves to indicate the likely NLTP period when construction of each of the projects could begin.
“NZTA will begin early planning for all projects by June 2025 and begin construction on some of the RoNS within the next three years, subject to funding.
“For RoNS projects where route protection is not in place, NZTA intends progressing with land designation and consents for these projects within the next 4 to 5 years, to provide long-term planning certainty for regions and communities.”
| Roads of National Significance | ||
|---|---|---|
| What | When | |
| Alternative to Brynderwyns | Contract signed | By end of 2027 |
| Whangarei to Port Marsden | Contract signed | By end of 2027 |
| Warkworth to Wellsford | Contract signed | By end of 2027 |
| Cambridge to Pairere | Prioritised | No date |
| Tauriko West State Highway 29Â | Protect route, design, consents | By end of 2027 |
| Mill Road | Progress early construction oppurtunities | By end of 2027 |
| East West link | Get project development and property purchase underway | No date |
| Hamilton Southern Links | Prioritised | No date |
| Petone to Grenada Link Road and the Cross Valley Link | No specifics | No date |
| North West Alternative State Highway (SH16)Â | No specifics | No immediate plans |
| Takitimu Northern Link Stages 1Â & 2 | Protect route, design, consents | By end of 2027 |
| Hawke’s Bay Expressway | Upgrade, start construction | By end of 2027 |
| Otaki to North of Levin | Start construction | By end of 2027 |
| Second Mt Victoria Tunnel and Basin Reserve upgrade | No specifics | No date |
| Hope bypass | Start construction | 2029 |
| Belfast to Pegasus Motorway and Woodend Bypass | No specifics | No date |
All up, the bill for the entire road and rail network will be $32.9 billion over the next three years.
Road users, through Road User charges, fuel taxes and registration fees, will provide $13.7 billion of that; local Government another $5.8 billion and through a variety of different votes, taxpayers will pay nearly $13 billion over the next three years to the New Zealand Transport Authority (NZTA) or as it is better known, Waka Kotahi.
The problem with that is the problem that all government budgets face.
What happens if road construction costs inflate beyond the allowances already built in by Treasury and NZTA.
NZTA Nicole Rosie was clearly concerned about that when she spoke to the media yesterday.
“What you will see published in the 24 to 27 document is a snapshot in time, the program of activities and projects,” she said.
“We have a big program of work ahead of us. And we know it will be challenging to deliver everything within the confines of our existing funding
“Costs for delivering transport programs continue to rise, and there is a shortage of skilled staff, as well as ongoing supply chain issues.
“These all tested our ability to meet our commitments given our limited financial constraints,
“But we are very much up for this program.”

Although cost remains a big worry, having a longer-term forecast of what work will be available should encourage the construction industry to keep a lid on costs.
“Input costs that have increased, such as the cost of doing business and construction, has increased over recent years, and Covid has had a big impact on it,” said Brett Glidden, NZTA General manager of Transport Services.
“But I think not having sustainable funding either over recent years has really impacted our ability to do things in an efficient way and to design a pipeline that allows construction companies to invest in plant and people to get efficiency.”
Underpinning this will be a $5.5 billion allocation for fixing potholes over the next three years.
“So, what we’re hoping with this new amount of money coming into the maintenance activity classes is that contractors can get a pipeline of work into the future that they will invest in growing people and other pieces of plant and better ways of doing things. So that’s the hope.”
Brown is also looking at getting additional money into NZTA from public-private partnerships and eventually congestion charging.
The Warkworth to Whangarei is likely to be a public-private partnership.
“We’re looking at accelerating that as a potential public-private partnership,” said Giddens.
“It will be delivered in stages, including the Brynderwyns, which we’ve started work on.
“We want to at least get the first, contract, awarded in the next couple of years so that we can make a start on that project.”

Though public-private partnerships are common overseas, they still require the Government to pay the project’s capital cost. The advantage is the timing of those payments can be extended.
Brown is open to any type of funding for the projects in the pipeline.
“I guess the expectation that we’ve set out is that the board should be considering all types of funding and financing for all of those major projects,” he said.
“So, in terms of whether it’s Mill Road or the road to Whangarei, our expectation is that the board (of NZTA) considers those funding and financing options.”
NZTA are likely to have to look at other funding options.
The Government already faces a squeeze on its operating allowance for next year’s budget, and though it can allocate capital outside the operating allowance, the likelihood that it will be able to cope with substantial cost inflation from Waka Kotahi is slim.
The Government has made big promises about delivering its Roads of National Significance, but it looks almost certain that it will not have many shovels in the ground at the time of the next election.
,